Tarka Boilers — Launch Board

From Launch Plan v2 · updated 27 July 2026
days to launch (~1 Sep)
59 / 150
waiting-list signups
62%
welcome email opens
10 jobs/wk
break-even (0% ads)
Waiting list
week of 20 Jul to 26 Jul · live from EmailOctopus
3this week
6 Jul
13 Jul
20 Jul
59 of 61 on the list are inside the service area (91 short of 150). Last week down 54 on the week before. No source tracking yet, so none of this can be traced to a group or a post.
Overall progress
Waiting, not stuck: the Week 1 post in Local Trades & Services (Barnstaple/Braunton/Georgeham) has sat in admin approval since 13 July. Leave it, do not resubmit.

Done so far

This week Mon 27 Jul – Sun 2 Aug · week 4 of 8

Week 5 3 – 9 Aug · site realignment

Week 6 10 – 16 Aug · ads + tracking

Week 7 17 – 23 Aug · staging

Ops setup any week before launch

Move week 24 – 30 Aug · keep it light

Launch day ~1 Sep

After launch Sep – Oct